ARLINGTON, Va., June 4 (UPI) -- It is now three months since the U.S. Air Force shocked the world by awarding the contract for its next-generation aerial-refueling tanker to Northrop Grumman and to the European Aeronautic Defense and Space Co., the European parent of Airbus.

Throughout that time, U.S. Air Force officials have insisted that the process by which the winner was chosen was transparent and fair. But the Air Force has failed to answer even the most basic questions about how the decision was made to deny the contract to Boeing, the widely favored incumbent. The U.S. Government Accountability Office is expected to issue a ruling on Boeing's protest of the outcome. Whatever it finds, the Air Force has some explaining to do.

Advertisement

First, the U.S. Air Force says it would cost roughly the same amount to develop, manufacture and operate 179 next-generation tankers, regardless of whether they are based on the Boeing 767 or the Airbus A330. But the Airbus plane is 27 percent heavier than the Boeing plane and burns more than a ton more fuel per flight hour. With fuel prices headed for the upper stratosphere, how can both planes cost the same amount to build and operate over their lifetimes?

Advertisement

Second, the U.S. Air Force says it would be equally risky to develop the Boeing tanker or the Airbus tanker -- after forcing Boeing to substantially increase the time and money required to develop its version. But Boeing proposed to build its tanker on the same assembly line where it already has constructed hundreds of the same airframe, whereas Airbus proposes to build its tanker at a plant and with a workforce that don't yet exist in Alabama. How can the risks be equal?

Third, the U.S. Air Force says that a computerized simulation of how the competing tankers would function in an actual wartime scenario strongly favored the larger Airbus plane. But the simulation assumed longer runways, stronger asphalt and more parking space than actually exist at forward bases, and failed to consider the consequences of losing bases in wartime. How can such unrealistic assumptions be relevant to the selection of a next-generation tanker?

Fourth, the U.S. Air Force says the Northrop-Airbus team received higher ratings on past performance than the Boeing team, based on a review of programs deemed similar to the future tanker. But Boeing built all 600 of the tankers in the current U.S. Air Force fleet, whereas Northrop and Airbus have never delivered a single tanker equipped with the refueling boom the Air Force requires. How can Northrop and Airbus have superior past performance?

Advertisement

I could go on. The U.S. Air Force refused to consider Boeing cost data based on 10 million hours of operating the commercial version of the 767, substituting instead repair costs based on the 50-year-old KC-135 tanker. It said it would not award extra points for exceeding key performance objectives, and then proceeded to award extra points. It said it wanted to acquire a "medium" tanker to replace its Cold War refueling planes, and ended up picking a plane twice as big.

Whatever else this process may have been, it definitely was not transparent. Even now, neither of the competing teams really understands why the competition turned out the way it did. It would be nice to hear from the U.S. Air Force about how key trade-offs were made, because at present it looks like a double standard prevailed in the evaluation of the planes offered by the two teams.

--